Environmental Risk

ActivitySituationAspectImpactInitial RatingDescriptionActionsResidual RatingSignificantControlled
OfficeNormalAir EmissionsElectricity UseLowUse of ElectricityEquipment switched off after hours and/or when not in use.
Where possible, implement energy saving functions and/or use energy saving light globes.
Zone lighting where practical.
LowNoNo
OfficeNormalRaw Materials - PaperLand FillLowUse of paper.Photocopies to have double sided print (default setting).
Paper to contain greater than 50% post consumer product.
Used paper to be collected for recycling.
Awareness signs to be displayed relating to recycling and waste of avoidance.
LowNoNo
Service DeliveryNormalWaste - PackagingLand FillLowPackaging WasteSource products from renewable/sustainable sources where possible.
Buy locally to reduce resource use and costs associated with transport.
Find suppliers that use less packaging or recyclable packing materials
LowNoYes
Service DeliveryAbnormalHazardous SubstancesContamination - Release of material of materials or substances to the environment.MediumRelease of hazardous substances during incidents/Small amounts of hazardous materials stored.
Materials and substances to be stored appropriately.
Spills to be reported to management and cleaned as soon as reasonably practical.
SDS to be maintained.
LowNoYes
Service DeliveryNormalWasteLand FillLowGeneral Waste generated by site activities.Effective waste management
Waste segregation & recycling.
LowNoNo
Service DeliveryNormalEnd of Life Disposal of Solar Panels, Inverters & BatteriesLandfillMediumDisposal of replace solar components.Recycling of components at eWaste Recycling Centres
Department of Energy Guidelines
LowNoYes
Service DeliveryNormalAir EmissionsUse of Fossil FuelsLowTravel to site and activities on site.Minimise Travel Use of local Subcontractors
Consolidated Transport - Drop Shipping
LowNoNo
Site ActivitiesNormalHazardous MaterialsContamination - ACM. Disturbance during Site ActivitiesMediumAsbestos identified on site.Disposal by licensed providers for areas greater than 10 msq
Disposal in accordance with regulations - Asbestos Terminology
LowNoYes
Site ActivitiesNormalEnergy EmissionsNoiseLowNoise generated by site activities.Noise pollution shall be minimised by ensuring that the normal working hours of the contract or project are adhered to whenever possible.

Working hours in accordance with specific conditions as specified by the nominated authorities

No work shall be performed outside these hours unless approvals have been obtained from the client & or the local regulatory authorities. No audible work shall take place between the hours of 7.00am & 8.00am Saturdays.
Local residents are to be advised of pending works in the area by means of a “letter box drop’ advising of possible noise disturbance.
All plant & machinery used shall have the necessary silencing mechanisms filled & be in good working order.
All requirements for the testing or monitoring of noise levels as specified by statutory authorities shall be performed in accordance with the required specifications & regulations
Consideration shall be given during the design Process for placement of equipment where it may cause noise disturbance to the public / residents
LowNoYes
Site ActivitiesNormalDisturbance of Land - ExcavationSoil to LandfillHighEffects of excavation.Project specific Environmental Management Plans
Excavation only be undertaken when no heavy rainfall is predicted and footings are then to be poured as soon as possible to minimise the exposure time.
Any excavated material shall be used to fill voids as appropriate.
Stockpile locations of material to be approved by the Principal prior to placement.
Correct methods for the disposal of waste.
MediumYesYes
Site ActivitiesAbnormalDischarge of WaterContaminated Storm Water Run OffMediumContaminated water run off from land disturbed by site activities.Only water of drinkable quality can be discharged into the drainage system.

Contamination can be pre-existing & found at the site during works or be the result of spillages, inappropriate protective measures, accidents or other abnormal activity.

Contaminated water can be recognised by:

An irregular or unnatural colour is noticed
A pungent smell is noticed
A visibly peculiar texture (chemical slicks, cloudy)
Any indicator of unusual water conditions are noticed
Contaminated land can be recognised by:

In irregular or unnatural colour is noticed
A pungent smell is noticed
A visibly peculiar texture (black tar, powdery texture)
Ant indicator or unusual soil conditions are noticed
LowNoYes
Site ActivitiesNormalCultural HeritageDisturbance, Damage or Removal of items of Cultural HeritageMediumAccidental disturbance of items of cultural significance during site activities.Prior to commencement of works at a site, items of heritage significance will be located and identified in the project specific Environmental Management Plan, so that construction practices may be modified to minimise disturbance to these items (e.g. where sandstone curb and gutter in a street is to be crossed, boring should be the means by which work is completed to minimise the risk of damage).
If any items of relics of Aboringinal or European heritage significance are identified during the project work will cease immediately at that location. Site Manager must be notified immediately who will notify the Principal to enable them to contact relevant authorities.
Consultation with traditional owner groups and confirmation of required induction and monitoring is to be undertaken by the Principal.
LowNoNo
Site ActivitiesAbnormalDischarge of WaterSoil ErrosionHighSoil errosion as a result of diverted water flow as a result of site activities.Install silt fences as required to prevent soil erosion MediumYesYes
Site ActivitiesAbnormalDisturbance of Land - ContaminationContaminated SoilMediumContaminated soil as a result of site activies including spills.Document emergency procedures to manage all reasonably foreseeable harm, including spills and other environmental emergencies
Obtain the agreement of the Principal to procedures for handling oil, chemicals and other dangerous goods before placing them on the Site, including secure storage arrangements
Inspect the Site regularly to ensure appropriate environmental controls are in place and operating effectively, and that all environmental management requirements are being met
LowNoNo
Site ActivitiesNormalHazardous Materials/WasteContamination - ChemicalsMediumContamination by chemicals used on site, including spills.Minimal use of hazardous chemicals on site.
Minimise the use of solvents, glues, paints and other materials which release odours or vapour
SDS Available
LowNoNo
Site ActivitiesNormalDisturbance of Land - ExcavationDustMediumDust generated by site activities.Dust control measures detailed in the Project Environmental Management Plan.LowNoNo

Aspects & Impacts